Corporate Atrium Kinetic Installation

A 9-floor corporate atrium requiring a visually calm but mechanically expressive centerpiece.

Constraints: High airflow variability, Low maintenance requirement, Tight installation window

Process: Developed modular fabrication units with balanced moving elements and controlled mass distribution.

Outcome: Completed in 14 weeks including installation, with periodic service interval documented at quarterly checks.

Budget Band: INR 12L - 18L